2 Proposed Timeline
Milestone |
Date |
Description |
---|---|---|
Approval required |
n/a
|
For details, see Approval to change |
Revised Technical Specification |
January 2025 |
AEMO releases new versions of this document as the technical requirements are streamlined. During the project this document is the source of truth From the production release, the technical specification becomes final and the related documents become the source of truth |
Related Documents publication |
Tuesday 2 September 2025 |
Release of guides and resources mentioned in Related documents |
MSUG meeting |
Wednesday 13 August 2025 |
Market Systems User Group Meeting (MSUG) to review the technical specification and ask AEMO technical SMEs questions This date is tentative. The Knowledge Management Team provides the invitation prior to the meeting |
Pre-production refresh |
24 - 28 August 2025 |
Refresh of the retail pre-production system with data from the production system. For more information, see Pre-production Refresh |
Pre-production implementation |
Tuesday 2 September 2025 |
AEMO implements components of the Release to pre-production for participant testing AEMO has full access to the system during this period Participant access is not restricted; however, the data content or system availability is not guaranteed |
Pre-production available |
Tuesday 9 September 2025 |
Testing period begins for participants |
Participant Testing |
9 September 2025 - 28 November 2025 |
Unstructured participant testing in the pre-production environment |
Production implementation |
Sunday 26 October 2025 |
AEMO implements the release to production |
Production systems available |
Sunday 26 October 2025 |
Production systems available to participants |